The project scope planning processes include all of the following EXCEPT: 


A)  how the project scope will be defined 
B)  how the requirements will be collected 
C)  how the work breakdown structure will be created 
D)  how the business case will be created

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

Which of the information below would NOT typically be included in the WBS dictionary for a specific work package?​ 


A)  description of the work 
B)  communication requirements 
C)  activities 
D)  expected duration

E) A) and C)
F) B) and C)

Correct Answer

verifed

verified

Which of the following statements concerning work packages is NOT correct?​ 


A)  Work packages are the basis for subsequent project planning activities. 
B)  Work packages are the basis for subsequent project control activities. 
C)  Work packages are activity elements with detailed descriptions of tasks and dependencies 
D)  Work packages are the elements at the lowest level of the WBS.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Failure to include project management in the WBS will increase the likelihood that the project will not be completed on time and within budget.

A) True
B) False

Correct Answer

verifed

verified

A WBS component is a work element that is part of the WBS at any level.

A) True
B) False

Correct Answer

verifed

verified

It is helpful to list requirements and supporting information in a requirements traceability matrix.When requirements are complete,they should meet all of these criteria EXCEPT:​ 


A)  Identified with the stakeholder(s) who needs it 
B)  Assigned to a team member who will be the requirement owner 
C)  Qualified by measurable conditions 
D)  Prioritized according to value, cost, time, risk, or mandate so trade-off decisions can be made if needed

E) A) and B)
F) C) and D)

Correct Answer

verifed

verified

Define Scope is the process of developing the:​ 


A)  project scope management plan. 
B)  detailed specifications of the project outcomes and products. 
C)  project work breakdown structure. 
D)  project scope network diagram.

E) C) and D)
F) A) and B)

Correct Answer

verifed

verified

A _______ is the approved project plan mainly consisting of scope,schedule,and cost that is not normally altered unless a  formal change control request is approved for modifying these plans.​ 


A)  requirement. 
B)  baseline. 
C)  benchmark. 
D)  component.

E) B) and D)
F) C) and D)

Correct Answer

verifed

verified

If a problem occurs during project execution,the WBS is helpful in understanding exactly where and why the problem occurred.

A) True
B) False

Correct Answer

verifed

verified

This technique is an iterative process that identifies and defines the work to be completely accomplished in the near term,and plans the future work at a higher level.


A)  Rolling wave planning. 
B)  Decomposition. 
C)  Traceability 
D)  Agile

E) A) and D)
F) C) and D)

Correct Answer

verifed

verified

Identify and describe the three steps that the team should follow in order to define project scope and create a project scope statement.

Correct Answer

verifed

verified

Key concepts to be covered in the respon...

View Answer

A deliverable is a condition or capability needed by a user to solve a problem or achieve an objective that satisfies a standard,a specification,or any other formally documented need.

A) True
B) False

Correct Answer

verifed

verified

A _________ is a written request or formal proposal to propose changes to any project planning component such as a document,project deliverable,or baseline (scope,cost,and time) .​ 


A)  scope statement 
B)  change request  
C)  project charter 
D)  request for proposal (RFP)

E) None of the above
F) A) and C)

Correct Answer

verifed

verified

Organizing the second level of the Work Breakdown Structure by major design components facilitates rolling wave planning.

A) True
B) False

Correct Answer

verifed

verified

Plan scope management is the process of creating a project scope statement.

A) True
B) False

Correct Answer

verifed

verified

Which of the following items best describes a project Work Breakdown Structure (WBS) ?​ 


A)  an organizational chart depicting who will perform project work 
B)  a schedule depicting when project work will be performed 
C)  a tool that the team uses to progressively divide deliverables into smaller and smaller pieces 
D)  a list of activities to complete the project work packages

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Which of the following is NOT a format that is typically used to represent a Work Breakdown Structure?​ 


A)  Hierarchical or "org chart" 
B)  Indented outline 
C)  Requirements Traceability Matrix 
D)  Free format

E) B) and C)
F) None of the above

Correct Answer

verifed

verified

A typical change request form will include which of the following content items?​ 


A)  a description of the change along with the impact expected from the potential change 
B)  a summary of previous changes to the project 
C)  an issues log 
D)  a change control process flow diagram

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

Once the plan baseline has been approved and the project is underway,project teams deal with change by establishing and using a change control system to receive and review change proposals and accept or reject them after evaluating their impact on project scope,cost and schedule.

A) True
B) False

Correct Answer

verifed

verified

It is important to assign a unique name and a unique number to every component in the project Work Breakdown Structure.

A) True
B) False

Correct Answer

verifed

verified